Chiller
Replacement of 2 compressors on York chiller
Radlett
Project Details
- Duration
- 3 days
- Project Value
- Between £15 000 and £17 500
- Engineers
- 3
- Scope of Work
- Replacement of 2 compressors on York chiller
About This Project
Both compressors on this York chiller had reached the end of their serviceable life and were causing the system to run inefficiently. Given the weight involved, a crane was brought in to manage the lifts. The old compressors were removed and overhauled replacements craned into position. Our engineers completed all electrical connections, re-pressurised the system and carried out thorough leak tests. The chiller was back online within the project window with full performance restored.