Air Conditioning
Installation of 5 Air conditioning units
Bristol
Project Details
- Duration
- 5 days
- Project Value
- Between £10 000 and £12 500
- Engineers
- 4
- Scope of Work
- Installation of 5 Air conditioning units including the interconnecting pipe work, electrics and drainage.
About This Project
Five indoor evaporators connected to three outdoor condensers across a large office - with the requirement that all pipework and cabling be routed underground throughout. That made it a precise job. Any damage or incorrect bend in the buried runs and the system would not function. Every route was carefully planned and tested before the floors were reinstated. All five units were commissioned and the office left clean on completion.
Project Photos